Road Closure

The Town of Marshfield is replacing four culverts on Maple Hill this summer.

Work on the Holt Rd culvert (replacing it with a bridge) begins on Monday, July 27. The culvert is between 581 and 692 Holt Rd. The road will be closed, and drivers will need to detour via Laird Pond Rd or around Maple Hill Rd. This project is expected to take approximately 5 weeks.

The next project will be a culvert on Laird Pond Rd near the pond- that road is expected to be closed for 4 weeks, and drivers will also need to detour. Intersections will be marked.

Another culvert on Maple Hill will be replaced later, with a shorter road closure, and the fourth culvert, on Pigeon Pond Rd, will have an on-site detour.